A new home on the Edwards Aquifer recharge or contributing zone falls under TCEQ's Edwards Aquifer rules, but many single-family lots do not need their own plan. TCEQ says an individual plan may not be required on a lot larger than five acres with one house, in a master community with an approved plan, or where impervious cover stays at or under 20 percent. Check the lot on the TCEQ map before design starts.

Key takeaways

  • TCEQ regulates only portions of the Edwards Aquifer, so start with the agency's map viewer.
  • A single-family home on a lot over five acres, with one house, may not need an individual plan.
  • Impervious cover includes the roof, driveway, slabs, sheds, and sidewalks.
  • A rainwater system that reuses roof water on the property can reduce the counted cover.
  • If a plan is required, TCEQ's review clock adds time before construction.

What does the Edwards Aquifer Protection Program regulate?

The program exists because the aquifer is karst. The TCEQ Edwards Aquifer Protection Program page explains that fractures, caves, sinking streams, and sinkholes act as conduits from the surface to the aquifer, so stormwater runoff or spills can reach the water quickly. It also says that before building on the recharge, transition, or contributing zones, you must first have your plan reviewed and approved by TCEQ.

That sounds broad, but the same page notes that only portions of the aquifer are regulated by TCEQ. The agency publishes an Edwards Aquifer Map Viewer so you can see whether a property sits over a regulated zone. For a lot near Dripping Springs, Wimberley, or Driftwood, or elsewhere in Hays, Travis, or Comal County, that lookup belongs in due diligence next to the survey and the flood zone check.

Does a single-family home need its own Edwards Aquifer plan?

Often it does not. The TCEQ private residences page says construction at private residences on the recharge or contributing zones is subject to the Chapter 213 rules, and it then lists conditions under which an individual plan may not be required for a single-family residence:

  • The residence is part of a master community with an approved plan.
  • The lot is larger than five acres, with no more than one single-family residence on it.
  • The residence and associated structures do not exceed 20 percent impervious cover within the property's legal boundaries.
  • A rainwater harvesting system captures roof water for beneficial reuse on the property and brings the adjusted cover to 20 percent or less.

The same page adds that demolishing an older development and building a new single-family home may require an application. If the property does not meet one of the listed conditions, TCEQ says an individual plan is required.

What counts as impervious cover on a home site?

More than the house. TCEQ's private residences page defines impervious cover as rooftops, driveways, concrete pads, sheds, sidewalks, or any impermeable surface that prevents water from soaking into the soil. On a smaller lot, a long driveway, a detached garage, a pool deck, and a covered patio can add up faster than the floor plan suggests.

That makes the site plan a permitting tool, not only a design drawing. Sketch every hard surface you expect to build, including future pieces such as a guest house or casita or a shop, and total them against the legal lot area. Our post on putting the site plan before the final floor plan explains why those decisions belong at the start.

Can rainwater collection lower the impervious cover count?

It can. The TCEQ private residences page says a rainwater harvesting system for a single-family residence may reduce the applicable impervious cover to 20 percent or less, as long as the water is put to beneficial use on the property, such as irrigation. Its example is a property with 37 percent cover that harvests from 18 percent of it, for an adjusted 19 percent.

TCEQ points owners to its technical guidance, RG-348, for the harvesting requirements. Collection systems have their own design questions about tanks, roof area, and treatment, which our rainwater collection guide covers.

How long does TCEQ take to review a plan?

If a plan is required, build its review into the schedule. The program page says administrative review can take up to 30 days, and technical review of an administratively complete application is 90 days, as outlined in 30 TAC 213.4(e). It also says the quality and completeness of the first submittal directly affect review time.

A required plan usually involves professionals such as an engineer or geologist, so it adds soft cost as well as time. The Central Texas cost guide covers how site studies and consultant fees fit into a budget, and our Hays and Travis County permit guide covers the county and city layers that still apply. For a custom home, these answers shape where the house and drive can go.

Frequently asked questions

How do I know if my lot is over the Edwards Aquifer?

Use TCEQ's Edwards Aquifer Map Viewer, linked from the Edwards Aquifer Protection Program page. TCEQ notes that only portions of the aquifer are regulated, so the map tells you whether the property sits over a regulated recharge, transition, or contributing zone.

Do I need a plan for one house on ten acres?

Possibly not. TCEQ says an individual plan may not be required when the lot is larger than five acres with no more than one single-family residence. Confirm the details with TCEQ's Edwards Aquifer staff before you rely on it.

Does a driveway count toward impervious cover?

Yes. TCEQ lists driveways with rooftops, concrete pads, sheds, and sidewalks as impervious cover, meaning any surface that keeps water from soaking into the soil within the property's legal boundaries.

Who answers Edwards Aquifer questions for Hays County?

TCEQ's private residences page lists Austin Region staff for Williamson, Travis, and Hays counties and San Antonio Region staff for Comal and several other counties. The program also takes questions at eapp@tceq.texas.gov.

Knowing the aquifer rules before design keeps the site plan honest. Use Build Studio to sketch a budget for the home you have in mind, or contact Ridge Rock Builders to talk through a specific lot.